Incineration Zistersdorf - historical milestones

model-zistersdorf

Around € 90 m investment, completion and beginning in May 2009.

Take a look at a flash presentation about the Waste-to-energy-plant in Zistersdorf, Austria


First Incineration March 2009

img
  • reinforcement railway connection
  • blowing out boiler
  • first waste delivery
  • first waste charging
read more

Construction Progress December 2008

img
  • turbine
  • transformer
  • emergency power diesel engine
  • rapper
read more

Construction Progress September 2008

  • img_4685Fluegas Treatment
  • Bunker Emergency Suction
  • Boiler Downcomer
  • Boiler Horizontal Fluegas Section
read more

Construction Progress June 2008

  • fotoFeeding Water Reservoir
  • Reception Hall - Veneer
  • Oil-Separator, Water Bassin and Slag-Hall
  • Boiler Casing above Grid
read more

Construction Progress March 2008

  • fotoConstruction works for rail connection
  • Heavy erection incineration
  • Completion of concrete works for energy building /turbine house
  • Nature conservation with biotope
read more

Construction Progress December 2007

  • fotoAssembling of bunker top at 34m
  • Administration building, bunker and stair towers
  • Auxiliary boiler
  • Slag-hall south view
read more

Construction Progress September 2007

  • fotoAuxiliary boiler and Compressor building Slag-Hall in the background
  • Bunker at 21,5m
  • Start earthmoving for railway connection
  • Administration building – workshop...
read more

Structural part bunker

  • fotoConstruction of bunker walls in progress
  • Bunker floor casted
  • Armoring bunker in execution
  • Improvement of the soil finished
read more

Construction groundbreaking ceremony of the first .A.S.A. incinerator

mvanews3_pic1DI Dr Helmut Wurian, general manager of .A.S.A. Abfall Service Zistersdorf GmbH and representatives of policy and economy, started on the 25th of May with the ground breaking ceremony the construction of the incinerator Zistersdorf...

read more

Waste treatment with sophisticated technique

largeview1

Principle

Environmental compatibility, Reliability of operation, Easy of operation...

read more

Signing General Contract

schemaGeneral contract signing with Von Roll Umwelttechnik AG after negotiations lasting for months...