.A.S.A. Austria
.A.S.A..A.S.A. AustriaIncineration Zistersdorf.A.S.A. Incinerator Zistersdorf

.A.S.A. Incinerator Zistersdorf

 

zistersdorf-en-1

NEW   Leaflet about the Waste-to-Energy plant in Zistersdorf (pdf)

 

Total Project Cost: € 90 Million

Main benefits of .A.S.A. Incinerator in Zistersdorf

  • Waste to energy process with highest efficiency
  • Certified as R1/R13 thermal recovery plant acc EU-guidelines
  • Bottom ash inert (less 1% TOC) and dumped in a very close landfill
  • Volume reduction (90%) and mass reduction (70%), savings of landfill space
  • Removal of scrap and use in steel industry
  • Savings of primary energy (comparable power production would need 40 million liters of oil)
  • Railway transport of 70% of the input material with less impact to the environment
  • Effective cleaning of flue gases
  • No effluents and less usage of potable water

Layout data

  • Fuel: Communal and Commercial waste
  • Incineration of 146,000 tons per year
  • Throughput up to 20 tons/h
  • Bunker capacity 7,300 m³ (7 days)

Operational data

  • 33 Employees
  • 1 incineration line
  • Dry flue gas treatment
  • No wastewater
  • 70% of waste delivered by train

Electricity production

  • Turbine: TGM Kanis
  • Generator: 15 MVA
  • Emergency Generator: 1,250 kW
  • Electricity production: 100,000 MWh/a = 30,000 Households

I. History

  • 1994/95: Environmental Impact Assessment (EIA), Design: Fichtner/Stuttgart
  • 1995: Submission of EIA Documents
  • 1997:  Hearing with Authorities
  • 1999: Approval (first instance)
  • 2004: Final Approval
  • 03/2006:  Decision to build the plant
  • 03/2007: Start of the construction
  • 10/2008: Pressure test of the boiler
  • 03/2009: First Fire
  • 11/2009: End of commissioning


Construction process in details can be found in the History section.

II. Incineration process in pictures

mva-scheme-en 


www.eco.at